| Return to the USDOJ/OIG Home Page |
Federal Bureau of Investigation's Management of Information Technology Investments
Report No. 03-09
December 2002
Office of the Inspector General
1. The FBI’s Management of IT Investments
The FBI is not effectively selecting, controlling, and evaluating its IT investments because it has not fully implemented any of the critical processes necessary for successful IT investment management. In the past, the FBI has not given sufficient attention to information technology investment management. As a result, the FBI continues to spend hundreds of millions of dollars on IT projects without having adequate selection and project management controls in place to ensure that IT projects will meet intended goals. However, since the FBI developed its ITIM Model and Transition Plan in January 2002, it has focused more management attention in this area and has made progress towards attaining a basic IT investment management foundation. Much of the progress has been in the “select” phase of the Plan, which was pilot tested in the Spring of 2002.
The ability of the FBI to completely implement the “control” and “evaluate” phases of the Plan, and achieve mature IT investment processes that can lead to enhanced mission performance, will require the FBI to increase its efforts in: (1) fully developing and documenting its new ITIM process; (2) requiring more input and participation from ITIM managers and users; and (3) further developing its project management and enterprise architecture functions. While the FBI recognizes many of these needs and has taken initial steps to address the needs, further action in these areas is needed to ensure that IT projects are developed within cost and schedule requirements, and meet performance expectations. The Trilogy project provides an example of how the non-implementation of fundamental IT investment management practices can put a project at risk of not delivering, within cost and schedule requirements, what was promised.
A. The FBI’s Progress Toward Attaining a Basic IT Investment Management Foundation
Although the FBI made measurable progress in improving its IT investment capability since it initiated a new ITIM process in early 2002, the FBI still lacks a complete foundation to build its IT investment maturity processes, and therefore is still in Stage One maturity.31 In the past, the FBI has not given sufficient management attention to IT investments. Because of the lack of management attention in the past, the FBI failed to implement the critical processes necessary to build an IT investment foundation. These critical processes include: (1) IT investment review board operation, (2) IT project oversight, (3) IT system and project identification and tracking, (4) business needs identification for IT projects, and (5) IT proposal selection.
(1) Importance of Attaining a Basic IT Investment Management Foundation
The primary purpose for attaining a basic IT investment management capability (Stage Two maturity) is to build the foundation for repeatable, successful IT project-level investment control and selection processes. Effective control processes over IT projects ensure that deviations from cost and schedule baselines can be identified and corrected. Selection processes ensure that the FBI has an effective methodology for approving only IT projects that are consistent with its needs and goals. According to the Framework, an organization can only achieve Stage Two maturity if it fully implements the following five critical processes:
To implement these critical processes, the FBI must execute a total of 38 key practices as defined in the Framework, or have alternative practices in place that are designed to achieve the same outcome.
At the start of our audit in January 2002, FBI officials told us that the Bureau was in the process of developing its new ITIM process. Although its ITIM process was still in the development stages, FBI officials told us that the FBI was executing certain key practices from Stage Two of the Framework. Additionally, the FBI officials said in March 2002 that they would pilot test ITIM processes pertaining to the selection of new IT proposals for the FY 2004 budget cycle. Further, the Plan establishes the FBI’s goal to fully attain Stage Two maturity for the FY 2005 budget cycle that starts in March of 2003, thereby establishing the foundation for enhanced investment capability.
(2) Summary of the FBI’s Progress Toward Attaining Stage Two Maturity
Based on the FBI’s responses to the self-assessment32 (and our validation of those responses), the FBI did not yet have in place any of the five critical processes associated with Stage Two maturity. However, since the FBI began pilot testing the select phase of its Plan in March 2002, it has made progress towards implementing the 38 key practices comprising the five critical processes - particularly in the area of selecting new proposals for IT projects. Specifically, at the beginning of our audit in January 2002, the FBI was only executing 4 of the 38 required key practices; however, as of June 2002, the FBI was executing 14 of the key practices. The following table provides a summary of the FBI’s progress toward implementing the key practices required for each critical process.
FBI Progress Toward Attaining Stage Two Maturity
| Critical Process | Status of ImplementingCritical Process | Total Key Practices Required | Key Practices Executed Prior to March 2002 | Key Practices Executed as of June 2002 |
|---|---|---|---|---|
| 1. IT Investment Board Operation | Not Implemented | 6 | 0 | 2 |
| 2. IT Project Oversight | Not Implemented | 11 | 1 | 2 |
| 3. IT Project Identification | Not Implemented | 7 | 1 | 2 |
| 4. Business Needs Identification for IT Projects | Not Implemented | 8 | 2 | 3 |
| 5. Proposal Selection | Not Yet Implemented, but Substantial Progress Made | 6 | 0 | 5 |
| Total | 38 | 4 | 14 |
| Source: OIG analyses |
For the remainder of section A of this finding, we provide detailed narratives of the FBI’s progress toward implementing each of the five critical processes. We also provide specific recommendations for expediting implementation of the critical processes and establishing more timely Stage Two maturity.
Each critical process contains core elements that provide the common framework for the process. For example, the organizational commitment element addresses the management actions that ensure the critical process is established and will endure; the prerequisites element addresses the conditions that must exist within an organization to successfully implement a critical process; and the activities element consists of the key practices necessary to implement a critical process. The key practices are the tasks within a core element that must be performed by an organization to effectively implement and institutionalize a critical process.
(3) Critical Process #1: IT Investment Review Board Operation
Depending on its size, structure, and culture, an organization may have more than one IT investment review board. The purpose of such boards is to ensure that basic policies for selecting, controlling, and evaluating IT investments are developed, institutionalized, and consistently followed throughout the organization. To establish a fully functioning investment review board, the FBI must execute the following six key practices:
The following table summarizes the FBI’s progress toward implementing fully functioning investment review boards.
FBI Progress Toward Implementing Fully Functioning Investment Review Boards (Critical Process #1)
| Key Practice | Key Practice Execution Status Prior to March 2002 | Key Practice Execution Status as of June 2002 |
|---|---|---|
| Organizational Commitment 1. An organization-specific IT investment process guide is created to direct each board’s operations. | Not Executed | Executed |
| Organizational Commitment 2. Organization executives and line managers support and carry out IT investment board decisions. | Not Executed | Not Executed |
| Prerequisite 1. Adequate resources are provided for operating each IT investment board. | Not Executed | Not Executed |
| Prerequisite 2. Board members understand the investment board’s policies and procedures and exhibit core competencies in using the IT investment approach via training, education, or experience. | Not Executed | Not Executed |
| Activity 1. Each IT investment board is created and defined with board membership integrating both IT and business knowledge. | Not Executed | Executed |
| Activity 2. Each IT investment board operates according to written policies and procedures in the organization-specific IT investment process guide. | Not Executed | Not Executed |
| Source: OIG analyses |
a. The FBI Has Executed Two of the Six Key Practices Associated with IT Investment Board Operation
We determined that the FBI executed two of the six key practices associated with implementing this critical process. Specifically, the FBI created an IT investment process guide containing policies and procedures to direct board operations (Organizational Commitment 1), and it created and defined three investment review boards integrating both IT and business knowledge (Activity 1).
Regarding the IT investment process guide (Organizational Commitment 1), in January 2002 the FBI issued its IT Investment Model and Transition Plan33 containing required guide elements prescribed by the Framework including:
Regarding the investment review boards (Activity 1), in June 2002 the Director approved board charters for each of the three investment review boards (the Executive Review Board, the Project Oversight Committee, and the Technical Review Board) that defined board membership and the responsibilities of board members.
The boards actually began functioning as early as March 2002, in conjunction with the FBI’s pilot testing of ITIM processes pertaining to the selection of new IT proposals for the FY 2004 budget cycle. Although board membership consists mostly of FBI managers who do not have extensive IT knowledge,35 the use of subject matter experts and reliance on the Enterprise Architecture Technical Committee36 can compensate for a lack of IT knowledge.
b. The FBI Must Execute Four of the Six Key Practices Associated with IT Investment Board Operation
Although progress has been made, the FBI does not have fully functioning IT investment boards because it still must execute four of the six key practices associated with this critical process. Specifically, the FBI must ensure that:
Regarding Organizational Commitment 2 and Activity 2, the approved charters for the investment review boards have been in effect since June 2002. Consequently, the FBI did not have sufficient data for us to assess whether managers and support staff effectively carried out board decisions and whether the boards operated according to the written policies and procedures contained in the Plan and board charters.
Regarding Prerequisites 1 and 2, in our judgment the FBI did not adequately plan sufficient time to ensure the IT investment boards operated effectively. Specifically, the FBI did not provide ample time between the initial draft of its Plan (January 25, 2002) and the March 2002 pilot testing of the select phase to adequately prepare and train IT board members. The DOJ originally instructed each component to begin developing an ITIM process in January 2001.37 In June 2001, the DOJ required each component to complete and submit to JMD an ITIM process and transition plan by the end of 2001.38 The DOJ also required each component to initiate the ITIM process for the FY 2004 budget cycle, which for the FBI began in March 2002. Consequently, the FBI had only one full month between the issuance of the Plan in late January 2002 and the initiation of the select phase of its ITIM process in early March 2002.
The ITIM Program Office Manager told us that the former FBI Chief Financial Officer would not approve the use of a contractor to assist in the development of the ITIM process earlier in the year. According to the former Chief Financial Officer, she had concerns that federal contracting regulations prohibited the FBI from using a contractor to perform a service that involves budget planning. However, following her transfer to another division in December 2001, the Information Resources Management Section received authorization to hire a contractor to assist with the development and implementation of the ITIM process.
We believe that without an ITIM contractor the FBI still had the opportunity to begin planning its ITIM process (including the training of board members) early in 2001. In fact, had the FBI better coordinated other ongoing efforts to develop processes that complement IT investment management, the FBI could have made significant strides in initiating its ITIM process during 2001 without expending additional resources. As discussed in section B of this finding, the FBI did not sufficiently incorporate (a) its enterprise architecture function (which was under development in 2001) and (b) the Project Management Process (issued in draft form in October 2001) into the development of its ITIM process. Enterprise architecture and project management not only complement the ITIM process, but also facilitate the maturation of ITIM. As discussed in section B of this finding, the FBI did not effectively utilize its internal resources when it developed its ITIM process through the use of a contractor because the FBI did not adequately consider the complementary, and potentially duplicative efforts that were already underway.
Not providing ample time resulted in inadequate training of board members and minimal preparation time to develop IT proposals. For example, Technical Review Board members had only 3 business days to review over 50 IT proposals prior to their first board meeting. FBI officials recognized these implementation issues in the Post-Implementation Review of the select phase pilot test.
In preparing board members for their duties, the FBI has thus far only provided one overview training session for board members and other users in the ITIM process. Additionally, while FBI officials have told us more ITIM training will be forthcoming, they have not provided us with any specific training plans for the future. Further, members of the Technical Review Board told us that board members, especially the Assistant Directors and EADs, do not have extensive knowledge in managing IT and must rely heavily on knowledgeable staff and other subject matter experts.
For the ITIM process to become institutionalized, the FBI must have a better training program. According to the Framework, board members should understand the board’s policies, roles, rules, and activities and be capable of carrying out their responsibilities competently. Education and training for members is needed in areas such as economic evaluation techniques, capital budgeting methods, and performance measurement strategies. The FBI’s Post-Implementation Review of the select phase pilot testing recommends “role-specific” training sessions for the following ITIM roles: (1) ITIM Liaison representatives,39 (2) Executive Review Board members, (3) Program Oversight Review Board members, (4) Technical Review Board members, and (5) ITIM stakeholders. It further recommends continuation of the overview training sessions previously provided, plus training for ITIM specific tools, such as the concept paper (containing the preliminary feasibility analysis), the OMB Exhibit 300 (containing the business case analyses), and IT proposal summaries.
FBI officials told us that time constraints were the main cause for not executing the four key practices identified above. As a result, there was insufficient time to introduce ITIM concepts to board members and other ITIM users. As mentioned above, the DOJ required each component to develop and begin implementation of an ITIM process for the FY 2004 budget cycle, which for the FBI begins in March 2002. Although FBI officials were aware of the requirement to initiate and adopt an ITIM process in January 2001, it was not until December 2001 that it began to develop its ITIM process. Had the FBI initiated more timely action to develop its ITIM process, it would have had significantly more time to prepare and train ITIM board members and other users. Without sufficient training and allocation of time to perform required tasks, the investment review boards cannot carry out their responsibilities to effectively select, control and evaluate projects.
c. Recommendations
We recommend that the Director of the FBI:
(4) Critical Process #2: IT Project Oversight
The purpose of this critical process is to ensure that the FBI’s investment review boards and project development teams provide effective oversight for its IT projects throughout all phases of the project life-cycle. IT investment boards generally review each project’s progress toward predicted cost and schedule expectations as well as anticipated benefits and risk exposure. The board members also employ early warning systems that enable them to take corrective actions at the first signs of cost, schedule, and performance slippages. Individual project development teams are responsible for meeting project milestones within the expected cost and schedule parameters.
Effective project oversight requires, among other things:
We concluded that the FBI is not effectively overseeing its ongoing IT projects. While the FBI maintained project management guidance and had three IT investment review boards in operation since March 2002, these activities have not adequately supported the FBI’s IT project oversight function. Our testing of the key practices associated with this critical process indicates that the FBI is executing only two out of the eleven key practices required to implement this critical process. The following table summarizes FBI progress toward implementing IT project oversight.
FBI Progress Toward Implementing IT Project Oversight (Critical Process #2)
| Key Practice | Key Practice Execution Status Prior to March 2002 | Key Practice Execution Status as of June 2002 |
| Organizational Commitment 1. The organization has written policies and procedures for project management. | Executed | Executed |
| Organizational Commitment 2. The organization has written policies and procedures for management oversight of IT projects. | Not Executed | Not Executed |
| Prerequisite 1. Adequate resources are provided to assist the boards in overseeing IT projects. | Not Executed | Not Executed |
| Prerequisite 2. Each IT project has and maintains an approved project management plan that includes cost and schedule controls. | Not Executed | Not Executed |
| Prerequisite 3. An IT investment review board is operating. | Not Executed | Executed |
| Prerequisite 4. Information from the IT asset inventory is used by the IT investment board as applicable. | Not Executed | Not Executed |
| Activity 1. Each project's up-to-date cost and schedule data are provided to the appropriate IT investment board. | Not Executed | Not Executed |
| Activity 2. Using established criteria, the IT investment board oversees each IT project's performance regularly by comparing actual cost and schedule data to expectations. | Not Executed | Not Executed |
| Activity 3. The IT investment board performs special reviews of projects that have not met predetermined performance standards. | Not Executed | Not Executed |
| Activity 4. Appropriate corrective actions for each under-performing project are defined, documented, and agreed to by the IT investment board and the project manager. | Not Executed | Not Executed |
| Activity 5. Corrective actions are implemented and tracked until the desired outcome is achieved. | Not Executed | Not Executed |
| Source: OIG analyses |
a. The FBI Has Executed Two of the Eleven Key Practices Associated with IT Project Oversight
While the FBI has project management guidance (and is therefore executing the key practice relating to the existence of project management methodology), the guidance is not being followed on a consistent basis. In fact, depending on whom we talked to, we obtained different answers as to which document represented the FBI’s official project management guidance.
For example, although IRD managers were aware that the DOJ’s System Development Life-Cycle is the FBI’s official project management methodology, they acknowledged that it is not consistently applied. Laboratory Division management officials told us that they do not follow the DOJ’s System Development Life-Cycle methodology, but rather have adopted their own project management system based on one used at the Department of Defense because it better meets their needs. CJIS Division management officials told us that although its Contract Administration Office is responsible for project management functions, they were not following any specific project methodology.
Other FBI personnel from the Information Resources Management Section told us the Project Management Process, developed by the FBI’s Inspection Division, was the FBI’s project management guidance. However, Inspection Division personnel indicated to us that the Project Management Process was still pending approval from the Director, as of June 2002. As a result, there appeared to be confusion among FBI officials as to what the official project management guidance was. As of June 2002, the Project Management Process had not been approved, nor was it being used to manage IT projects.
As previously discussed in the prior report section pertaining to the investment review board critical process, the FBI established three IT investment review boards in March 2002 (the Executive Review Board, the Project Oversight Committee, and the Technical Review Board). Although the investment review boards are operating, the boards have not yet been involved in project oversight. As the ITIM process continues to evolve, project oversight by these boards should increase accordingly.
b. The FBI Must Execute Nine of the Eleven Key Practices Associated with IT Project Oversight
Based on our analyses, the FBI does not have effective IT project oversight because it has not yet executed nine out of the eleven key practices associated with this critical process. Specifically, the FBI must ensure that:
Regarding Organizational Commitment 2, the FBI has not developed written policies and procedures for management oversight of IT projects. While the Plan provides a conceptual basis for board oversight of IT projects and the board charters define the boards’ responsibilities, the FBI does not have the specific policies and procedures in place for overseeing and controlling projects. FBI officials have acknowledged to us that the Plan was never intended to represent the complete and final policies and procedures for management oversight of IT projects. The Plan states that it is a fluid document that will need to be modified and supplemented as the pilot test is performed. As a result, FBI officials recognize that additional policies and procedures must be developed. As of June 2002, FBI officials have told us they are in the process of developing these specific policies and procedures for the control phase of the ITIM pilot test.
Regarding Prerequisite 1 (providing adequate resources to the boards), we concluded that this key practice has not been executed because as of June 2002, the FBI did not have a functioning project management office to assist the boards in overseeing IT projects. The Plan calls for a functioning project management office to assist the boards, especially the Project Oversight Committee, and consequently is a necessary resource for IT project oversight. As of June 2002, the FBI has not yet utilized its project management function to assist the Project Oversight Committee in IT investment decision-making.
The functioning project management office represents a critical resource to the Project Oversight Committee and thus to IT project oversight. In our judgment, the functioning project management office needs to have jurisdiction over IT projects throughout the Bureau, rather than limit its responsibilities to division-specific projects. Until June 2002, the FBI lacked a functioning project management office that had jurisdiction over IT projects throughout the Bureau. Rather than having a centralized project management office, independent of individual divisions, the FBI maintained three separate division-level project management offices to manage IT projects. These three separate project management functions were maintained in the IRD, CJIS, and Laboratory Divisions, contributing to inefficiencies in project coordination and the risk of “stove piping” projects. Because of its importance in supporting the ITIM process, the subject of establishing and maintaining a centralized project management office is further discussed later in this report.
Regarding Prerequisite 2, we determined that each IT project does not have an approved project management plan that includes cost and schedule controls. Personnel from the IRD project management office told us that generally IT projects with high visibility have project management plans that include cost and schedule controls. However, other lower visibility projects have less rigid controls in place. This condition developed because the IRD project management office did not uniformly enforce the development of project management plans by all IT project managers. In our judgment, projects under the IRD’s discretion have not been adequately controlled. Although personnel from the CJIS and Laboratory Divisions indicated that IT projects under their respective divisions did have management plans with cost and schedule controls, without a functioning board that approves and monitors these project management plans FBI managers have no assurance that IT projects are effectively managed in accordance with uniform standards.
Regarding Prerequisite 4, the FBI has not yet developed an IT asset inventory; consequently, the FBI’s investment review boards are not aware of all the IT projects and resources for which the boards are responsible. FBI managers told us they were in the process of developing an IT asset inventory. However, at the time of our audit they were unable to provide an estimated date for completing the inventory. Unless the investment review board members are fully cognizant of the IT projects and resources for which they are responsible, the boards cannot exercise effective oversight of ongoing IT projects. Additional details pertaining to the FBI’s plans to finalize the IT inventory are provided later in this report.
Finally, since the IT investment review boards were not involved in overseeing IT projects as of June 2002, we concluded that none of the five remaining key practices activities have been executed. These five key practices are the basic activities that investment review boards must implement to effectively oversee IT projects during the control phase. The FBI provided us documentation indicating that the Project Oversight Committee (the primary IT investment review board responsible for overseeing IT projects) met in June 2002 to discuss the FBI’s intent to pilot test the control phase of the Plan by September 2002. The documentation stated that the FBI was still working on designing the specific procedures associated with the control phase, including integrating the ITIM process with the project management office. Additionally, the FBI has only provided us with summary information on when and how the control phase of the ITIM process will be rolled out. The information lacks specific details needed to effectively implement this critical process.
FBI personnel told us that the lack of established IT investment review boards (prior to March 2002) was the main cause for ineffective project oversight. Additionally, they stated that the control phase of the ITIM process would be pilot tested by September 2002. However, the FBI has not been able to provide us with a specific timeline as to: (1) how the pilot test will be executed, and (2) details as to how the ITIM process will interface with a project management methodology. These issues are further discussed in Section B of this finding.
Without effective oversight of IT projects, FBI officials do not have adequate assurance that IT projects are being developed on schedule and within established budgets. As described in the following paragraphs, the lack of effective IT project oversight has contributed to the FBI’s problems in managing IT projects, including a lack of accountability for cost and schedule overruns, a lack of consideration for full life-cycle costs, and lost credibility with Congress.
According to a former Chief Information Officer at the FBI, the lack of effective oversight of IT projects (as a result of not having IT investment review boards and a centralized project management office) have prevented IT project managers from being held accountable for cost and schedule overruns and the ultimate performance of projects. For example, the former Chief Information Officer told us that the CJIS Division completed the Integrated Automated Fingerprint Identification System and the National Crime Information Center 2000 years behind schedule and millions of dollars over budget. He also told us that management changes in the CJIS Division have not occurred, despite these overruns. Senior FBI officials also told us that the Bureau’s budget formulation process focuses only on the acquisition costs for IT projects and not the full life-cycle costs, especially operations and maintenance costs. For example, an assessment performed by the FBI’s Inspection Division on the Trilogy project40 noted that the life- cycle cost estimate is inadequate and only focuses on the term of the contract, not the life of the project. FBI personnel told us that a lack of consideration for full project costs is not limited to Trilogy, but also applies to other IT projects. Without accountability for significant deviations from project baselines, there is a lack of incentives for project managers to adequately control and evaluate projects.
According to FBI officials, the FBI’s inability to effectively complete IT projects within budget and schedule reduced the FBI’s credibility in the eyes of Congress. The lack of credibility contributed to delays in the FBI receiving Congressional funding to upgrade its IT infrastructure. This subject, along with how Trilogy may be adversely affected because of uncertainties in determining projected costs and scheduled completion dates for project milestones, is further discussed in section C of this finding.
c. Recommendations
We recommend that the Director of the FBI ensure:
(5) Critical Process #3: IT Project and System Identification
For the FBI to make effective IT investment decisions, it must have at its disposal information about existing IT investments as well as the proposed investments being considered. The purpose of this critical process is to provide the IT investment boards the information required to fully evaluate the impacts and opportunities created by both the proposed and current IT investments. The key practices of this process require the FBI to identify and track the IT projects and systems within the organization to create a comprehensive inventory. According to the Framework, effective identification of IT projects and systems requires:
While the FBI has taken steps to identify its IT projects and systems in an IT asset inventory, it still does not have a complete IT asset inventory that is being using by the IT investment review boards for investment management purposes. As part of an enterprise architecture data repository, the FBI is developing a comprehensive inventory of its IT projects and systems. In addition, FBI officials have told us that the enterprise architecture office is primarily responsible for developing and maintaining the data repository. However, the data repository has not been completed, nor have board members used its contents during the select phase of the ITIM process that took place during the Spring of 2002. The FBI’s enterprise architecture function is further discussed in section B of this finding. The following table summarizes the key practice ratings for the IT project and system identification critical process.
FBI Progress Toward Identifying IT Projects and Systems (Critical Process #3)
| Key Practice | Key Practice Execution Status Prior to March 2002 | Key Practice Execution Status as of June 2002 |
| Organizational Commitment 1. The organization has written policies and procedures for identifying its IT projects and systems and collecting an inventory that includes information about the IT projects and systems that is relevant to the investment management process. | Executed | Executed |
| Organizational Commitment 2. An official is assigned responsibility for managing the IT project and system identification process and ensuring the inventory meets the needs of the investment management process. | Not Executed | Executed |
| Prerequisite 1. Adequate resources are provided for identifying IT projects and systems and collecting relevant information into an inventory. | Not Executed | Not Executed |
| Activity 1. The organization's IT projects and systems are identified and specific information about these projects is collected in an inventory. | Not Executed | Not Executed |
| Activity 2. Changes to IT projects and systems are identified and changed information is collected in the inventory. | Not Executed | Not Executed |
| Activity 3. Information from the inventory is available on demand to decision-makers and other affected parties. | Not Executed | Not Executed |
| Activity 4. The IT project and system inventory and its information records are maintained to contribute to future investment selections and assessments. | Not Executed | Not Executed |
| Source: OIG analyses |
a. The FBI has Executed Two of the Seven Key Practices Associated With Identifying IT Projects and Systems
Based on our analyses, we determined that the FBI has executed two of the seven key practices associated with this critical process. Specifically, the FBI has developed written policies and procedures for identifying its IT projects and systems in an inventory that includes information relevant to the investment management process (Organizational Commitment 1). Additionally, the FBI has designated an official responsible for managing the IT project and system identification process and ensuring that the inventory meets the needs of the investment management process (Organizational Commitment 2).
Regarding Organizational Commitment 1, we determined that the FBI has developed adequate written policies and procedures for: (a) identifying its IT projects and systems and (b) collecting information relevant to the investment management process on each project and system. Prior to December 2001, the FBI did not have written policies and procedures for identifying IT projects and systems. The FBI did, however, provide us with an electronic communication dated December 3, 2001 from the enterprise architecture staff that was distributed Bureau-wide requesting management from each division to provide information on its IT systems. The information obtained from the divisions is used by the enterprise architecture staff to develop the data repository of IT systems.
Regarding Organizational Commitment 2, the FBI has designated the Chief Architect of the enterprise architecture office with responsibility for managing the IT project and system identification process and ensuring that the inventory, when completed, meets the needs of the investment management process and ITIM managers and users. The Chief Architect currently reports to the Information Resource Management Section Chief, who reports to the Chief Information Officer.
b. The FBI Must Execute Five of the Seven Key Practices Associated with Identifying IT Projects and Systems
Although the FBI has made recent progress in identifying IT projects and systems, the FBI does not have a comprehensive IT project and system identification process because it still has not executed five out of the seven key practices associated with this critical process. Specifically, the FBI must ensure that:
Regarding Prerequisite 1, FBI managers told us that the FBI has not allocated adequate resources to ensure timely and successful completion of the IT project and system identification critical process. FBI managers from the Information Resources Management Section told us that they do not have sufficient staffing to support the ITIM process, including the enterprise architecture function. The enterprise architecture office within the Information Resources Management Section plays a key role in the ITIM process as it assists the Technical Review Board and maintains the data repository information on IT systems and projects. Further, personnel who we interviewed from the enterprise architecture office told us that limited staffing was a factor in not having the data repository completed.41
Regarding the remaining four key practices, none of those practices can be executed until the FBI completes the creation of its IT asset inventory. More importantly, the IT asset inventory will have little value to the FBI if it is not used when making IT investment decisions. Prior attempts at compiling an inventory of IT projects were used to satisfy Congressional and DOJ requests, rather than to assist the IT investment management process. For example, the FBI prepared a partial list of its information technology projects to comply with a Congressional request in August 2000.
FBI officials informed us that they anticipate the investment review boards will use the completed inventories to contribute to future investment selections and assessments. The Plan states that the FBI must establish a complete IT portfolio set as the ITIM process matures. Further, FBI personnel told us that the enterprise architecture data repository, when complete, will be available to decision-makers and other ITIM users via the FBI’s Intranet. However, we have not been provided with a specific timeframe for when the FBI expects to have a completed inventory. FBI personnel told us that the primary cause of not having a completed IT asset inventory and actively using it in the ITIM process is because of staffing shortages. While that may be a contributing factor, we concluded that the lack of centralized management over IT investments was also a limiting factor. As a result, certain divisions maintained some version of an IT inventory for the projects and systems under their jurisdiction, and there was no centralized office responsible for maintaining a uniform listing Bureau-wide.
Without a complete IT asset inventory in the ITIM process, FBI management and board members do not have adequate assurance that accurate, timely, and complete information on existing IT projects and systems is available to them. As a result, there is a risk that new IT proposals selected overlap with one of the 200 or so existing FBI applications. While the recently established review boards helped to mitigate this risk for the FY 2004 budget selection process, we believe that an IT asset inventory must be used by the boards to optimize the use of the FBI’s resources.
c. Recommendations
We recommend that the Director of the FBI:
(6) Critical Process #4: Business Needs Identification
This critical process establishes the mechanism for identifying the business needs and the associated users that drive each IT project. This critical process links the organization’s business objectives with its IT strategy and creates the partnership between the users and the IT providers. According to the Framework, effective identification of business needs requires:
While the FBI has made progress in identifying business needs for IT projects, it has not yet executed all the key practices necessary to implement this critical process. Prior to pilot testing the select phase of its ITIM process in March 2002, the FBI had been identifying users for each IT project in the Exhibit 300.42 Since pilot testing the select phase of the ITIM process beginning in March 2002, the FBI has used a concept paper along with the Exhibit 300 to identify and define business needs. In addition, the FBI has defined its general business needs and goals in its strategic plan, which is further discussed later in this report. However, as previously mentioned, the FBI has not identified all of its IT projects in an asset inventory; consequently, progress in implementing this critical process is contingent upon completing the FBI IT inventory. Also, we were not provided evidence indicating that identified users participate in project management throughout a project's life-cycle. The following table summarizes the key practice ratings for the business needs identification critical process.
FBI Progress Toward Identifying its Business Needs (Critical Process #4)
| Key Practice | Key Practice Execution Status Prior to March 2002 | Key Practice Execution Status as of June 2002 |
|---|---|---|
| Organizational Commitment 1. The organization has written policies and procedures for identifying the business needs (and the associated users) of each IT project. | Not Executed | Not Executed |
| Prerequisite 1. Adequate resources are provided for identifying business needs and associated users. | Not Executed | Not Executed |
| Prerequisite 2. The organization has defined business needs or stated mission goals. | Executed | Executed |
| Prerequisite 3. IT staff are trained in business needs identification. | Not Executed | Not Executed |
| Prerequisite 4. All IT projects are identified in the IT asset inventory. | Not Executed | Not Executed |
| Activity 1. The business needs for each IT project are clearly identified and defined. | Not Executed | Executed |
| Activity 2. Specific users are identified for each IT project. | Executed | Executed |
| Activity 3. Identified users participate in project management throughout a project's life-cycle. | Not Executed | Not Executed |
| Source: OIG analyses |
a. The FBI has Executed Three of the Eight Key Practices Required to Identify its Business Needs and Associated Users
We determined that the FBI has executed three of the eight key practices associated with this critical process. Specifically, the FBI has defined its business needs or stated mission goals (Prerequisite 2); the business needs for identified IT projects are clearly identified and defined (Activity 1); and specific users are identified for each IT project (Activity 2).
Regarding Prerequisite 2, we determined that the FBI has defined business needs or stated mission goals. The FBI has stated mission goals in its strategic plan. The FBI’s strategic plan has not been updated since 1998, but the Director has revised the priorities of the Bureau since the terrorist attacks on September 11, 2001. Further, the FBI is currently in the process of developing an enterprise architecture framework, which will link the FBI’s strategic plan to its business needs.
Regarding Activity 1, we determined that the business needs for each IT project are clearly identified and defined in the Exhibit 300. Prior to the initiation of the ITIM pilot test in March 2002, the FBI did not have adequate management controls in place to ensure that the business needs for each project were accurately developed in the Exhibit 300. With the ITIM process, the board reviews of the concept papers and Exhibit 300s provided assurance that these business needs were clearly identified and defined. In instances where the business needs were vague, the boards, especially the Technical Review Board, returned the concept papers and Exhibit 300s to the project sponsor for re-work. This re-work demonstrates that board review of these IT proposals was an effective control over the business needs identification process. Our review of Exhibit 300s that were ultimately recommended to the Executive Review Board for inclusion in the FY 2004 budget cycle confirmed that business needs were clearly identified and defined.
Regarding Activity 2, the FBI identified specific users for each IT project. Based on our reviews of several Exhibit 300s both before and after the initiation of the ITIM process in March 2002, we determined that the users for the IT project were identified and documented.
b. The FBI Must Execute Five of the Eight Key Practices Required to Identify its business Needs and Associated Users
Although progress has been made in identifying its business needs and associated users, the FBI has yet to execute five of the eight key practices associated with this critical process. Specifically, the FBI must ensure that:
Regarding Organizational Commitment 1, we determined that the FBI does not have written policies and procedures for identifying the business needs (and the associated users) of each IT project. The FBI has been defining business needs for IT projects in the Exhibits 300 and related concept papers. The Post-Implementation Review acknowledges that the FBI needs more formally developed policies and procedures to support the ITIM process. By formalizing these procedures in writing, the FBI reduces the risk that it will neglect to perform this practice in the future.
Regarding Prerequisites 1 and 3, FBI officials told us that adequate resources were not allocated to identifying business needs and associated users. Specifically, FBI officials from the Information Resources Management Section told us that there has not been sufficient resources dedicated to the ITIM process, including the training of ITIM users. The importance of training ITIM users in the many facets of the ITIM process cannot be underestimated. Part of the required ITIM training must include the business needs identification process. Examples of training in this critical process include organizational requirements for ongoing education, rotation of ITIM users through supported business units, and relevant conference attendance. As previously mentioned, many ITIM users have only received one training session on the FBI’s ITIM process. Additionally, the FBI has not provided us with specific plans for future training sessions that include business needs identification. As a result, these key practices have not been executed.
The ITIM training that occurred in February 2002 provided only an overview of the ITIM process, rather than role-specific training that addressed the business needs identification. The Post-Implementation Review stated that re-work of Exhibit 300s and concept papers were required after these products were submitted to the ITIM program office. This re-work was necessary because there was not a clear alignment between the IT proposal and the FBI’s strategic goals. Better training that included business needs identification may have reduced some of the re-work. Further, a more clearly defined enterprise architecture framework would have increased the IT staff’s knowledge in business needs identification.
Regarding Prerequisite 4, as previously mentioned, the FBI has not completed its IT asset inventory. Identifying all projects in an IT asset inventory is a fundamental step in having a fully developed business needs identification process. The availability of this inventory assists board members in recommending IT projects that support one or more business needs or mission goals.
Regarding Activity 3, FBI officials have acknowledged that identified users do not consistently participate throughout the project’s life-cycle. FBI officials informed us that not keeping IT system users actively involved in the creation and implementation of IT projects is a major factor in the development of multiple IT systems (including ACS) that do not effectively meet user needs. When we asked the former Chief Information Officer for other examples of systems that do not effectively meet user needs, his response was “pick one.” Clearly, this is a significant need that must be addressed by the ITIM process. The DOJ’s System Development Life-Cycle requires user participation throughout the life-cycle, but as we previously noted in this finding, the System Development Life-Cycle is not used by the FBI on a consistent basis. Board oversight of project teams should be required to ensure that users are engaged throughout the project’s life-cycle.
FBI officials told us that there has not been ample time since the implementation of the Plan to adequately train its IT staff and board members in business needs identification. A complete explanation as to why the FBI did not have ample time for training was previously discussed in section A.3 of this finding.
Although FBI officials have told us that additional training for IT staff and board members is expected to occur sometime in the future, we were not provided evidence that shows there will be any training specifically related to business needs identification. Further, we have not been provided with a timetable as to when this training will take place. In addition, an effective business needs identification process requires an organization to have a comprehensive IT portfolio and enterprise architecture, neither of which the FBI currently has. Our assessment of the FBI’s efforts to implement a basic enterprise architecture is discussed later in this report.
Without a comprehensive business needs identification process, FBI management and board members do not have adequate assurance that they are selecting IT projects that align with mission needs and priorities. Additionally, projects under development are at risk of not meeting the needs of users, as has been the case with ACS and other FBI systems.
c. Recommendations
We recommend that the Director of the FBI ensures:
(7) Critical Process #5: IT Proposal Selection
The proposal selection critical process establishes a structured methodology for selecting new IT proposals. The FBI should have this critical process fully implemented to ensure that it selects the most meritorious IT proposals to meet its mission critical needs. According to the Framework, this critical process requires:
The following table summarizes the key practice ratings for the proposal selection critical process.
FBI Progress Toward Establishing an IT Proposal Selection Process (Critical Process #5)
| Key Practice | Key Practice Execution Status Prior to March 2002 | Key Practice Execution Status as of June 2002 |
|---|---|---|
| Organizational Commitment 1. Executives and managers are committed to follow an established selection process. | Not Executed | Executed |
| Organizational Commitment 2. An official is designated to manage the proposal selection process. | Not Executed | Executed |
| Prerequisite 1. Adequate resources are provided for proposal selection activities. | Not Executed | Not Executed |
| Activity 1. The organization uses a structured process to develop new IT proposals. | Not Executed | Executed |
| Activity 2. Executives analyze and prioritize new IT proposals according to established selection criteria. | Not Executed | Executed |
| Activity 3. Executives make funding decisions for new IT proposals according to an established process. | Not Executed | Executed |
| Source: OIG analyses |
a. The FBI Has Executed Five of the Six Key Practices Associated With Establishing an IT Proposal Selection Process
As previously discussed, the FBI pilot tested its ITIM proposal process in March 2002. The Plan outlined a conceptual framework for selecting projects, while subsequent documents further defined the process. We determined that the FBI has executed five of the six key practices associated with this critical process. The five key practice are:
Regarding Organizational Commitment 1 and Activity 1, we concluded that in pilot testing its proposal selection process in March 2002, FBI managers were committed to and followed an established selection process for the FY 2004 budget cycle.
Prior to the initiation of the ITIM process in March 2002, the FBI did not have an established process for selecting IT proposals. Several FBI officials told us that individual divisions determined their IT needs in a “stovepipe,” without knowledge of the business needs and priorities of the Bureau as a whole. Once each division decided on its IT request, the request was forwarded to the Information Resources Management Section for a “technical” review. This review, performed by the Information Resources Management Section Chief, was designed to ensure that the request was consistent with the FBI’s existing IT infrastructure. However, without an established enterprise architecture, the review could not adequately provide assurance that the proposal aligned with the FBI’s business needs and priorities.
Once approved by the Information Resources Management Section Chief, the request was then forwarded to the Finance Division to determine if similar requests for budget enhancements were previously denied by Congress. Requests approved by the Finance Division were forwarded to a committee comprised of executive managers for final evaluation and selection. However, personnel from the Finance Division told us that it was not uncommon for the IRD, Laboratory, and CJIS Divisions to submit requests for IT projects that were duplicative but were approved anyway. This indicates that the Information Resources Management Section did not adequately perform its role in overseeing IT proposals. Additionally, according to FBI officials, the committee of executive managers did not have a formalized charter, follow approved polices or procedures, or maintain documentation detailing committee activities. Therefore, the process was not standardized or repeatable.
With the initiation of the ITIM process in March 2002, the FBI established a proposal selection process for the FY 2004 budget cycle. IT proposals were developed by the project sponsor with a preliminary feasibility analysis, referred to as a concept paper. The concept paper was submitted to the Enterprise Architecture Technical Committee for a preliminary technical review, and then forwarded to the Technical Review Board with a recommendation as to whether the project should be approved. Upon the Technical Review Board’s approval, the project sponsor was asked to prepare a more comprehensive business case analysis, which was documented in the Exhibit 300. The project proposal package, which includes the concept paper and Exhibit 300, was then submitted to the Project Oversight Committee for a business review. The Project Oversight Committee assembled the multiple requests and recommended a list of projects for the Executive Review Board’s review. The Executive Review Board selected projects for the FY 2004 budget cycle. Because this process was documented in the Plan, and enhanced with training materials, we concluded that the FBI effectively established a selection process. The following flowchart outlines the FBI's proposal selection process.
FLOWCHART OF FBI’S ITIM SELECT PHASE

Source: FBI’s training materials for the ITIM process as of February 2002.
Regarding Organizational Commitment 2, prior to the initiation of the select phase of its ITIM process in March 2002, the FBI did not have a clearly designated official to manage the proposal selection process. According to Information Resources Management Section personnel, the Finance Division managed the IT selection process. However, according to Finance Division personnel, the Information Resources Management office was responsible for managing the proposal selection process. With the onset of the ITIM process in March 2002, the FBI’s Chief Information Officer appointed the ITIM Program Manager to manage the proposal selection process. This official reports to the Information Resources Management Section Chief, who reports to the Chief Information Officer.
Regarding Activity 2, we determined that FBI IT investment board members analyzed and prioritized new IT proposals according to established selection criteria for the FY 2004 budget cycle. Projects were prioritized according to three separate areas: (1) mission fit; (2) technical criteria (including risk management and architectural assessments); and (3) financial criteria (including performance measures, cost/benefit analyses, and acquisition strategy).
Regarding Activity 3, the three IT investment review boards made funding decisions for new IT proposals according to a process established for the FY 2004 budget cycle. The Executive Review Board, chaired by the Director, had the final authority for making IT funding requests to the DOJ. The Executive Review Board members based their decisions upon recommendations made by the Technical Review Board and the Project Oversight Committee. Based on the use of an established process, this key practice has been executed.
b. The FBI Must Execute One Key Practice Associated With Establishing an IT Proposal Selection Process
Although the FBI has made substantial progress in establishing an IT proposal selection process for the FY 2004 budget cycle, in our judgment it has yet to allocate adequate resources for comprehensive proposal selection activities. Our conclusion is based upon the following observations.
Without a comprehensive proposal selection process that includes adequate resources and training, the FBI cannot ensure that it is selecting the best IT projects that meet mission-critical needs.
c. Recommendations
(8) Overriding Cause for the Lack of an FBI IT Investment Management Foundation
Although the GAO ITIM Framework was originally published in May 2000, the underlying key practices needed to implement each critical process are, in essence, tasks that are fundamental to any project management endeavor. Some of these tasks include the prerequisite conditions that must be in place in an organization to successfully implement critical processes. These tasks involve allocating resources, establishing organizational structures, and providing training. Another group of tasks include the organizational commitments that ensure critical processes will endure. These tasks involve establishing organizational policies and engaging senior management sponsorship. A third group of tasks include the activities necessary to implement the critical processes. These tasks involve establishing procedures, performing and tracking the work, and taking corrective actions as necessary.
Although these tasks are fundamental to effective project management, the majority of these tasks had not been executed by the FBI to select and manage its IT resources. Prior to the development of its ITIM process in early 2002, the FBI did not give sufficient attention to IT investment management. Organizational policies were not clearly established to ensure that critical IT investment policies endure. Additionally, there were no clearly defined, uniform procedures for project management, tracking project performance, and taking corrective actions as necessary.
Because the FBI did not fully implement any of the critical processes associated with Stage Two, the FBI continues to spend hundreds of millions of dollars on IT projects without having adequate selection and project management controls in place to ensure that IT projects will deliver their intended benefits. However, the FBI has made progress in improving its IT investment process since it initiated a new ITIM process in early in 2002. Although further action is required, the launching of the ITIM process represents improvement in the FBI’s ability to mitigate the risks that IT projects will not deliver their intended benefits. Whether the FBI can achieve further improvement depends on whether the Plan addresses the remaining key practices not being executed as well as the FBI’s ability to completely implement the Plan and fully establish its ITIM process.
B. The FBI’s Ability to Improve its IT Investment Practices
As previously noted, the FBI lacks a foundation necessary to build its IT investment capabilities, and therefore, is in Stage One maturity. However, in January 2002, the FBI developed an ITIM plan to build a foundation for selecting, controlling, and evaluating IT investments. Additionally, during the course of our audit fieldwork (from January 2002 to June 2002), the FBI initiated its ITIM process, as defined by the Plan. Consequently, the FBI made progress towards implementing the Plan, especially in the area of IT proposal selection.
Because the FBI was only in the beginning stages of implementing the Plan during our audit fieldwork, we assessed the FBI’s ability to progress through the more advanced stages of the framework necessary to improve its IT investment maturity. Our assessment of the FBI’s ability to improve its IT investment management consisted of the following four areas:
Our evaluation of these four areas, documented in the following sections, includes both the FBI’s strengths and weaknesses in each area. In our judgment, the FBI’s efforts in these areas are critical to its ability to maximize the effectiveness of its ITIM process, and ultimately improve mission performance.
(1) The Plan’s Coverage of Stage Two Key Practice Activities That Were Not Being Executed During Our Fieldwork
The FBI’s IT Investment Management Model and Transition Plan addresses the select, control, and evaluate key practice activities necessary to build an IT investment foundation. However, the Plan requires further development to ensure effective implementation. Because the Plan was intended to be a conceptual framework, it was not written to fully describe the specific policies and procedures of the select, control, and evaluate phases of the ITIM process. Without further development of the ITIM process, the FBI will have difficulty making additional progress in improving its IT investment management practices, especially in the control and evaluate phases.
a. Importance of the Plan’s Coverage of Stage Two Key Practice Activities
Because the Plan stated that its purpose is to establish and define the FBI’s Stage Two methodology necessary to build an IT investment foundation, we examined the Plan’s coverage of Stage Two key practice activities. The FBI was pilot testing the select phase of the ITIM process during our audit fieldwork. As previously noted, we determined that the FBI executed 14 of 38 Stage Two key practices, mainly in the area of proposal selection. Of the 24 key practices that were not executed, 11 specifically related to activities associated with the control and evaluate phases of the ITIM process. Although the FBI had made little progress in executing activities from the control and evaluate phases of the Plan during our fieldwork, we examined the Plan to determine whether it adequately addressed the 11 Stage Two key practices activities associated with the control and evaluate phases that were not being executed. The ability of the FBI to achieve Stage Two maturity is dependent, in part, on the adequacy of the Plan.
In JMD’s assessment of the Plan, JMD rated the Plan against elements it considered necessary to comply with GAO, OMB, and DOJ guidelines. JMD’s assessment indicated that the Plan complied with the criteria used.44 Additionally, JMD’s assessment stated that although the Plan does not fully address a few items, such as the exact criteria that will be used to select and evaluate investments, it does provide a schedule for completing these items.
Our assessment of the Plan focused on whether it addressed the Stage Two maturity key practices in the GAO ITIM Framework and our conclusions are consistent with those from JMD.
b. Results of Our Assessment of the Plan’s Coverage of Stage Two Key Practice Activities Associated with the Control and Evaluate Phases
In our judgment,the FBI’s IT Investment Management Model and Transition Plan addresses the 11 Stage Two key practice activities, on a conceptual level, that were not being executed during our fieldwork. Because the key practice activities are addressed conceptually, further development is needed to clearly define these activities and to determine how these activities can be implemented.
Our analyses (previously documented in this report) indicated that the FBI was not executing one or more key practice activities in each of the following Stage Two critical processes: (1) IT investment board operation; (2) IT project oversight; (3) IT project and system identification; and (4) business needs identification. As previously discussed, 11 of the key practice activities necessary to implement these four critical processes relate to the control and evaluate phases of the Plan. The tables below describe how the Plan addresses the key practice activities that we determined were not being executed during our audit testing.
| IT Investment Board Critical Process | |
|---|---|
| Key Practice Activity Not Executed | How the Plan Addresses the Activity |
| Activity 2: Each IT investment board operates according to written policies and procedures in the organization-specific IT investment process guide. | While the Plan does not provide the specific written policies and procedures that the investment boards must follow, it does indicate that further development of these policies and procedures are necessary. Additionally, the Post-Implementation Review of the select phase of the ITIM pilot test recommends that additional policies and procedures be developed in a document that is independent of the Plan. Once the FBI’s ITIM policies are completely developed, this key practice can be executed when the FBI rolls-out the control and evaluate phases of the ITIM process. |
| Source: OIG analyses |
| IT Project Oversight Critical Process | |
|---|---|
| Key Practice Activity Not Executed | How the Plan Addresses the Activity |
| Activity 1: Each project's up-to-date cost and schedule data are provided to the appropriate IT investment board. | The Plan stipulates that the functioning project management office will review status reports on cost, schedule, and performance measures. The project management office will then forward selected reports to the boards for review. |
| Activity 2: Using established criteria, the IT investment board oversees each IT project's performance regularly by comparing actual cost and schedule data to expectations. | The Plan states that the Project Oversight Committee will ensure that selected projects are meeting performance measurement objectives, risks are being appropriately managed, budgets and schedules are on track, and resource levels are adequate. |
| Activity 3: The IT investment board performs special reviews of projects that have not met predetermined performance standards. | According to the Plan, the Project Oversight Committee will perform special reviews of projects whose status reports are not meeting predetermined performance standards. |
| Activity 4: Appropriate corrective actions for each under-performing project are defined, documented, and agreed to by the IT investment board and the project manager. | The Plan states that the Project Oversight Committee will review a portfolio status report to determine if quick corrective actions can be executed to get under-performing projects back on track. When this is not possible, appropriate recommendations will be made to the Executive Review Board. |
| Activity 5: Corrective actions are implemented and tracked until the desired outcome is achieved. | The Plan gives the Project Oversight Committee the responsibility to ensure that corrective actions are implemented. |
| Source: OIG analyses |
| IT Project and System Identification Critical Process | |
|---|---|
| Key Practice Activity Not Executed | How the Plan Addresses the Activity |
| Activity 1: The organization's IT projects and systems are identified and specific information about these projects and systems is collected in an inventory. | The Plan states that an IT investment portfolio will be built for development projects as the ITIM process is being pilot tested. An IT portfolio is expected to be completed for the full-blown ITIM roll-out during the FY 2005 budget cycle. |
| Activity 2: Changes to IT projects and systems are identified and change information is collected in the inventory. | FBI personnel told us that while there is not a written procedure to document changes to IT projects and systems, a policy will be developed when the IT asset inventory is complete. The IT asset inventory will then be updated as changes are made to IT projects and systems. |
| Activity 3: Information from the inventory is available on demand to decision-makers and other affected parties. | FBI personnel stated that the IT asset inventory, when complete, will be maintained on the FBI’s Intranet, so that relevant information will be available on demand to decision-makers and other affected parties. |
| Activity 4: The IT project and system inventory and its information records are maintained to contribute to future investment selections and assessments. | FBI personnel stated that the IT asset inventory and IT portfolio, when complete, will be updated continually to become an archive of information to be used for future investment selections and evaluations. |
| Source: OIG analyses |
| Business Needs Identification Critical Process | |
|---|---|
| Key Practice Activity Not Executed | How the Plan Addresses the Activity |
| Activity 3: Identified users participate in project management throughout a project's life-cycle. | The Plan states that it is crucial for project team members (which must include identified users of the project) to work closely together throughout the project’s life-cycle. These project teams support the functional project management office and Project Oversight Committee. |
| Source: OIG analyses |
With the pilot testing of the select phase, the FBI further developed and refined the proposal selection process and provided training on proposal selection to ITIM users. The training materials supplemented and supported the documentation in the Plan to more clearly define the roles of ITIM users, such as IT investment review board members, project sponsors, and ITIM liaison representatives.
Even with these additional materials, the Post-Implementation Review of the select phase of the Plan (performed by the ITIM contractor) recommended that the FBI significantly expand its documentation of polices and procedures relating to the ITIM process by:
The FBI recognized that the Plan was never intended to represent its final policies and procedures for its ITIM process. The Plan states that it provides a conceptual framework for achieving Stage Two maturity, and will evolve as the FBI’s ITIM process advances to higher levels of maturity.
Without further development and refinement of the ITIM process, the FBI will have difficulty making additional progress in improving its IT investment management practices. Because the goal of Stage Two maturity is to build standardized methodologies for selecting and controlling IT investments, the FBI must have adequate documentation of these methodologies to make them repeatable and institutionalized. The Post-Implementation Review, prepared by the ITIM contractor, acknowledged the necessity for further developing and refining the Plan. In our judgment, the FBI must implement the recommendations set forth in the Post-Implementation Review prior to taking further action in pilot testing the control and evaluate phases of the ITIM process.
c. Recommendation
(2) The Amount of Participation from ITIM Users in Developing the ITIM Process
In our judgment, the Plan was written with minimal input and coordination from relevant ITIM users. The main reason cited by IRD officials46 for the limited participation from ITIM users was insufficient time allotted to develop the Plan. As a result, the institutionalization and buy-in47 of the ITIM process may have been hampered.
a. Importance of ITIM User Participation in Developing the ITIM Process
Good management practices dictate that organizations involve relevant stakeholders when attempting to implement a new management process. This involvement aids in the institutionalization of the process. Institutionalization of the ITIM process is a key goal of the Plan, which states: “[The ITIM] process applies to ALL information technology projects, from ALL business units, from ALL funding sources, whether they be new, in development or operational.”
Because of the broad applicability of the ITIM process, in our judgment the FBI should have involved representatives from throughout the Bureau when developing the Plan. In particular, individuals from the three divisions that manage major IT projects (the IRD, CJIS, and Laboratory Divisions) should have had substantial input into the creation of the Plan. Further, the Inspection Division’s Major Project Management Oversight Unit (MPMOU) has a responsibility to oversee major projects in the Bureau, including IT projects, and thus should also have been involved in creating the Plan.
b. Results of Our Assessment of ITIM User Participation in Developing the ITIM Process
We found that relevant ITIM users from the IRD, CJIS Division, Laboratory Division, and Inspection Division were not given significant input into how the Plan was developed. Our interviews with IRD personnel indicated that the FBI gave the ITIM contractor the primary responsibility to write the Plan, without requiring significant participation from ITIM users in developing the initial draft of the Plan. Additionally, we determined that while the contractor interviewed numerous individuals from the IRD, it only interviewed two people from the Inspection Division, one person from the CJIS Division, and none from the Laboratory Division.48 Further, as we discuss below, the enterprise architecture office (part of the IRD until February 2002) was not given adequate input into the development of the ITIM process. Also, the interviews that did occur outside of IRD mainly focused on the individuals’ current responsibilities for managing IT investments, rather than their insights into how the new ITIM process could be shaped to best meet the needs of the Bureau. The following paragraphs provide the perspectives of ITIM users from the IRD, CJIS Division, Laboratory Division, and the Inspection Division.
Personnel from the enterprise architecture office told us that because the FBI’s ITIM process had been developing concurrently with the enterprise architecture function, there should have been more coordination between the ITIM contractor and enterprise architecture office to increase effectiveness and reduce duplication of effort. For example, the enterprise architecture office drafted charters for a three-tiered IT investment review board structure, similar to what was ultimately written by the ITIM contractor. Additionally, the enterprise architecture office was preparing initiatives to improve the FBI’s IT investment management practices. While the enterprise architecture office was drafting board charters and other processes designed to improve the FBI’s IT investment management practices, the ITIM contractor, supervised by the ITIM Program Office, wrote the Plan without incorporating the work already accomplished by the enterprise architecture office.
Additionally, an individual from the enterprise architecture office told us that although he believed the ITIM process represents a positive step for the FBI, it must incorporate more involvement from the enterprise architecture function to ensure success of the process. He further stated that the IT investment review boards must rely more on the vast knowledge, expertise, and talents of FBI IT personnel prior to making decisions.
Further, according to a manager in the Information Resource Management Section, the Enterprise Architecture Technical Committee, which supports the Technical Review Board, has not been given the responsibility to ensure that IT proposals align with the mission of the FBI. The responsibilities of the Technical Review Board, as defined in the Plan, are focused on reviewing the technical risks of IT projects. These technical risks include compliance with the “technical architecture” or configuration management of the FBI, rather than the business architecture which shows how the business processes work together to satisfy the mission. The Plan and board charters assigned this responsibility to the Project Oversight Committee. In our judgment, because the responsibilities of the enterprise architecture office comprise both the technical and business architecture, the Enterprise Architecture Technical Committee should not only be responsible for assessing compliance with the technical architecture, but should also be responsible for assessing compliance with the business architecture. This added responsibility would provide greater assurance to FBI executives that IT proposals selected will enhance the Bureau’s capability in achieving its mission.
An official from the CJIS Division told us that he was interviewed by representatives from the ITIM contractor on one occasion to determine what role the CJIS Division had in managing IT projects. However, he was not consulted on how the FBI’s ITIM process should be created. He stated the only opportunity he had to comment on the Plan was after it was written in January 2002. His belief was that the ITIM Program Office was relying solely on the contractor to write the Plan, rather than building a Plan that has the input and buy-in from all FBI divisions.
While this official from the CJIS Division said to us that the Plan was an improvement over the FBI’s current process for managing IT investments, he was not convinced that the process could be effectively implemented without addressing other pressing issues, such as the need for: (1) standardized methodologies in configuration management, quality assurance, and IT security; (2) improved support of contractors that work on IT systems; and (3) more representation of individuals with IT technical expertise on the IT investment review boards.
An official from the Laboratory Division’s project management office told us that he first became aware of the Plan when training was announced for the new ITIM process in February 2002. Another official from the Laboratory Division told us that to his knowledge, no one from the Laboratory Division was consulted by the ITIM contractor prior to the preparation of the Plan. He told us that the Laboratory Division’s current process was working fine and not in need of change.
Additionally, Inspection Division personnel, including individuals from the MPMOU, told us (as of June 2002) they were only consulted by the ITIM contractor as to how they acquired IT, not for their project oversight role.
An official from the Information Resources Management Section cited the insufficient amount of time allotted to prepare the Plan as the main cause for the limited involvement from ITIM users. As we previously mentioned, the FBI waited until December 2001 to engage the ITIM contractor to develop the Plan, despite learning of the DOJ’s requirements to prepare a plan in January 2001. The ITIM Program Office Manager stated that the former Chief Financial Officer did not initially approve the use of an outside contractor to develop the Plan, causing a delay in hiring the contractor. The former Chief Financial Officer confirmed to us that there were initial concerns in using an outside contractor to develop a management process that affects how the IT budget is allocated and spent. Because the DOJ required initiation of the ITIM process during the FY 2004 budget cycle (which for the FBI begins in March), there was limited time between the development of the Plan (December 2001) and the initiation of the ITIM process (March 2002). In fact, the FBI only gave the contractor approximately two weeks to write the Plan because of the impending deadline to submit the Plan to JMD. As a result, FBI personnel told us that the ITIM contractor did not have ample time to include more ITIM users in the Plan’s development.
While FBI officials from the Information Resources Management Section acknowledged the ITIM contractor’s time constraints in developing the Plan, they also stated that the Plan is only a draft, and will be modified as the ITIM process is pilot tested. Additionally, because the three IT investment review boards established by the ITIM process include representatives from the major divisions that manage IT projects, officials from the Information Resources Management Section told us that there is significant opportunity for input into refining the ITIM process as it is being pilot tested.
Despite the Information Resource Management Section’s position that the pilot test provides ample opportunity for input into refining the ITIM process, in our judgment, the ITIM Program Office, along with the ITIM contractor, continues to develop the ITIM process without incorporating sufficient input from relevant stakeholders. For example, a manager from the enterprise architecture office stated to us in July 2002 that the ITIM Program Office had not requested his participation during development of the control phase of the ITIM process. This individual told us the enterprise architecture function should have a role in enhancing the control and evaluate phases of the ITIM process, but has not had the opportunity to demonstrate this role. Additionally, the process for the development of the control phase has not substantially changed from the select phase: the ITIM contractor, supervised by the ITIM Program Office, writes the policies and procedures which are then pilot tested by the ITIM users. In our judgment, this approach is not conducive to a process whose success depends on institutionalization and buy-in from ITIM users.
c. Summary
In our judgment, the lack of involvement by relevant ITIM users inhibits management buy-in to the ITIM process. If there had been more participation in the development of the Plan, some of the concerns stated above by key ITIM users might have been mitigated. The FBI must address these concerns to facilitate the institutionalization and buy-in the of the ITIM process, and ultimately improve its effectiveness.
d. Recommendations
(3) The Project Management Function’s Support of the ITIM Process
The FBI’s project management function needs improvement to adequately support the ITIM process, especially in the control and evaluate phases of the process. The FBI recognizes the importance of upgrading the project management function. In particular, the Plan states that the project management office must fulfill a critical role in supporting the Project Oversight Committee. In addition to the Plan, the FBI has taken other steps towards improving its project management function. Specifically, in June 2002, the FBI announced plans to create an Office of Programs Management. The Office of Programs Management will serve as a centralized project management office49 that FBI officials from this office and the Information Resources Management section expect to play a key role in implementing the ITIM process. Despite the progress being made, the FBI still has critical areas to address, such as integrating a project management methodology with its ITIM process.
a. Relationship Between Project Management and ITIM Numerous legislative mandates, including the Results Act and the Clinger-Cohen Act, require federal agencies to establish and maintain processes for managing systems throughout their life-cycle. These legislative mandates indicate that basic project management practices are essential if an organization is to ensure that its IT projects have established cost, schedule, and technical performance baselines that are monitored throughout the project’s life-cycle. Additionally, project management is fundamental to supporting an ITIM process. In particular, the control phase of an ITIM process requires an organization to have a project management function. For example, IT project oversight, which encompasses basic project management practices, must be implemented for an organization to achieve Stage Two maturity. However, the Framework does not by itself provide a comprehensive model for how an organization should develop its project management function.
According to the Framework, an ITIM process is not a substitute for good project management. While an ITIM process takes an enterprise-wide focus, good project-level management forms the foundation for successful IT investments.
In our judgment, for the FBI’s project management function to effectively support its ITIM process, the Bureau must have: (1) a fully operational centralized project management office whose responsibilities are directly integrated with the ITIM process, and (2) a standardized project management methodology that is integrated with the ITIM process. Because of the importance of these efforts, we assessed the FBI’s progress in integrating these areas with its ITIM process.
b. Importance of a Centralized Project Management Office
The Plan recommends that project teams be staffed from a “pool” of managers and developers maintained in the project management office. These project teams would not be dedicated to solely one division, function, or application; instead, these teams would work on all types of IT projects across the Bureau. According to the Plan, this approach has many benefits, including:
We concur with the Plan’s recommendations. Although the Plan does not specifically state that the project management office should be centralized (independent of any division), in our judgment, such a structure is most conducive to attaining the benefits listed above.
In addition to the above benefits, a centralized project management office can ensure that IT project teams are following a standardized project management methodology that is integrated with the ITIM process. In our judgment, this added control is especially important to the FBI since we previously concluded that the FBI’s three main divisions that manage IT projects (the IRD, CJIS, and Laboratory Divisions) have not been consistently using a standardized project management methodology.
c. Importance of a Standardized Project Management Methodology
The DOJ recognized the importance of integrating project management with the ITIM process. In January 2001, it issued DOJ Order 2880.3 to require components to manage IT investments in a way that demonstrates good stewardship, complies with applicable laws, and accomplishes the agency’s diverse mission. Among its policies, the Order required each DOJ component to establish an ITIM process that is integrated with a structured system development life-cycle methodology. While the FBI is mandated to use the DOJ’s System Development Life-Cycle methodology, we previously stated in this report that it has not been used consistently.
d. Results of Our Assessment of the FBI’s Progress in Integrating its ITIM Process with the Responsibilities of a Centralized Project Management Office
As discussed below, we concluded that the FBI has recently made progress in integrating its ITIM process with the responsibilities of a centralized project management office. Not only does the FBI recognize the importance of this integration, but it has taken major steps towards incorporating the ITIM process with the responsibilities of a centralized project management office. This progress was evidenced by: (1) how the Plan defined the role of the project management function, and (2) the FBI’s recent efforts to establish a centralized project management office.
The Plan recommends centralization of IT investment management through the use of IT investment review boards that have Bureau-wide oversight. Of the FBI’s three IT investment review boards, the Project Oversight Committee has the primary responsibility for controlling IT projects. Additionally, the Plan calls for a project management office, a subcommittee of the Project Oversight Committee, to have discretion in managing IT projects Bureau-wide.
Specifically, the Plan defines how the primary responsibilities of the project management office must be integrated with the activities of the ITIM process, particularly during the control and evaluate phases. These responsibilities include:
We were told in June 2002 that the Director of the FBI approved the creation of a centralized project management office, whose chief executive would report to the Director.50 This project management office, which would be independent of all other FBI divisions, would have the primary responsibility of managing projects in the Bureau. These projects would include, but not be limited to, information technology. The proposed mission for this new office is: “To assist the FBI in effectively managing, implementing, and deploying high-priority, complex and high risk development projects of high dollar value to successfully support the FBI’s operational mission.” To achieve this mission, this office will be:
In addition, the Office of Programs Management has the following core functions for which it will ultimately be responsible: (1) system engineering, (2) schedule, (3) budget, (4) risks, (5) contract management, (6) certification and accreditation of IT systems, (7) configuration management, and (8) quality assurance.
In our judgment, the creation of the Office of Programs Management represents a critical first step towards centralizing the project management function and improving its effectiveness. Additionally, officials from the Information Resources Management Section and the Office of Programs Management have told us that they are working together to facilitate the integration of the responsibilities of the eight core functions listed above. The ITIM process needs the full support of the Office of Programs Management to implement the control and evaluate phases of the Plan. Therefore, in our judgment, the FBI should continue its efforts to integrate the responsibilities of the Office of Programs Management with the ITIM process. Specifically, a plan should be developed that outlines activities that must be performed to complete the integration, along with reasonable suspense dates. Additionally, this plan should provide the criteria and thresholds that the Office of Programs Management will use to select IT projects for review.
e. Results of Our Assessment of the FBI’s Progress in Integrating its ITIM Process with a Standardized Project Management Methodology
We concluded that the FBI has not taken the necessary actions to integrate the ITIM process with a standardized project management methodology. While officials from the Information Resources Management Section have acknowledged to us that the ITIM process needs to be integrated with a standardized project management methodology, they have not taken sufficient action to ensure that these processes are integrated in a timely manner. This conclusion is evidenced by the Information Resources Management Section’s lack of coordination with the Inspection Division’s Major Project Management Oversight Unit (MPMOU), as previously reported in this section. Additionally, as discussed in the following paragraphs, the FBI risks duplicating efforts in managing IT projects if it implements the control and evaluate phases of the ITIM process without integrating these phases first with a standardized project management methodology.
To improve the FBI’s ability to manage projects, including IT projects, the prior FBI Director requested that the MPMOU establish a standardized project management methodology for Bureau-wide use. In October 2001, the MPMOU completed the Project Management Process and submitted it to executive management for approval. The Project Management Process, which incorporates the DOJ’s System Development Life-Cycle methodology, provides a framework that encompasses all phases of a project’s life-cycle, including planning, developing, support, and disposal.
Personnel from the MPMOU stated to us that the Project Management Process provides a mechanism to fulfill certain requirements of the ITIM process. Specifically, personnel from the MPMOU told us that the project management process facilitates the ITIM process by:
According to MPMOU personnel, given their knowledge of the FBI’s requirement to develop an ITIM process, they made repeated attempts beginning in 2001 to work with individuals from the Information Resources Management Section to develop these processes concurrently.
In November 2001, personnel from the MPMOU prepared a presentation entitled “Project Management Process Compatibility with the ITIM Process” to show appropriate individuals from the IRD the similarities between the two processes. However, according to MPMOU personnel, individuals from the IRD who were managing the development of the ITIM process never gave MPMOU the opportunity to make th